What is the 10 year cost for the Recreation Center?

| | Comments (0) | TrackBacks (0)

Town of Moultonborough

6 Holland Street · Post Office Box 139

Moultonborough, N.H.  03254

(603) 476-2347

 

Municipal Needs Committee

2008 Town Warrant Supporting Material

Presented to Selectboard March 6, 2008

 

The Municipal Needs Committee had a work session on March 4th and the below two Warrant Articles were a matter of concern and discussion:

 

ARTICLE 9

To see if the Town will vote to raise and appropriate the sum of $375,000.00 for architectural, engineering, and related fees relative to the eventual construction of a community/senior center, fields, and related outdoor improvements.

 

ARTICLE 10

To see if the Town will vote to establish an expendable general trust fund, with the Selectmen as agents to expend, under the provisions of RSA 35:1 to be known as the Community/Senior Center Fund for the purpose of constructing and/or developing a community/senior center and related expenses and to raise and appropriate the sum of $100,000.00 toward this purpose.

 

 

To assist the Selectboard and members of the community who ask “What is the $475,000 for?” the MNC has prepared the attached one page summary document.  Values are extracted from the RSPT proposal and appendices.  The new RSPT promotional flyer omits critical data needed for decision-making.

 

The warrant requests a specific dollar amount because the RSPT does have a specific concept to buy design plans for and do have specific cost estimates that were the basis for the A&E request. The MNC believes these initial cost estimates should be openly shared with the public.  The MNC used the voluminous RSPT documents to produce a chart  summarizing projected costs over the ten-year bond period.  It identifies areas where costs were omitted demonstrating the burden will be higher than stated. Revenue and fees are not yet  disclosed and excluded here.

 

Given the effort of the MNC to fully grasp the details within the ambitious RSPT proposal, the MNC wanted to share that same level of understanding with the Selectboard, and anticipate you will then share this with the public. 

 

 

2008 Town Warrant Supporting Material

 

ARTICLE 9

To see if the Town will vote to raise and appropriate the sum of $375,000.00 for architectural, engineering, and related fees relative to the eventual construction of a community/senior center, fields, and related outdoor improvements.

 

ARTICLE 10

To see if the Town will vote to establish an expendable general trust fund, with the Selectmen as agents to expend, under the provisions of RSA 35:1 to be known as the Community/Senior Center Fund for the purpose of constructing and/or developing a community/senior center and related expenses and to raise and appropriate the sum of $100,000.00 toward this purpose.

 

What is this funding for?  What is the anticipated future project cost?

 

 

          Item Description                          Item Cost                              Comments                                      

Article 9: A&E and Fees

Town Warrant 2008

       $   375,000                             

Approx 8% of estimated project cost to refine projected costs, finalize design plus some additional site analyses

RSPT Estimated Bldg Cost

      $ 5,024,000

Pg. 35 RSPT proposal

Interest on 10 Yr Bond

      $ 1,247,500

$5 M @ 4.25% for 10 Years

 

Projected Operating Costs over 10 Year Bond

(Adds 4 Full-time plus 4 Part-time employees to Recreation Staff)

      $ 3,198,300

RSPT proposal appendix  (amount omits annual maintenance costs after year-one warranties expire, and excludes annual inflation factor on salaries, benefits, etc.)

Recreation Fields and Beach Improvements

     $ 1,536,000

Pg. 6 RSPT proposal  (amount omits any future maintenance  costs)

Recreation Feasibility Study

      $      50,000

Town Meeting 2006 authorization

Initial Lion’s Club purchase

      $    495,000

Town Meeting 2007 authorization

 

Projected Total Recreation Study & Implementation

     $11,925,800+

 

Full RSPT proposal in today’s dollars

 

 

Average Annual Cost - 10 Years

    $ 1,200,000+

Approx $0.42 per $1000/Assessed Value

 

Omitted Operational Costs

  $  ??????+

Adds approx.  5% - 10% annually

 

NOTE:  After the bond is fully paid, operational costs will run about $500,000 annually (or $0.25 per $1000/Assessed Value) before any future expansion.

Future Site Expansion

       $ ??????

Pool ($2,286,000 + interest + annual operating costs and 7 more staff members) pulled from  consideration by RSPT Dec ‘07

 

0 TrackBacks

Listed below are links to blogs that reference this entry: What is the 10 year cost for the Recreation Center? .

TrackBack URL for this entry: http://moultonboroughcitizensalliance.org/blog/mt-tb.cgi/101

Leave a comment

About this Entry

This page contains a single entry by Jim published on March 14, 2008 1:08 PM.

Misinformation brochure distributed in Moultonborough was the previous entry in this blog.

Community Center is the next entry in this blog.

Find recent content on the main index or look in the archives to find all content.

Powered by Movable Type 4.01